The emergency and exit lighting installed was manually tested, halogen and fluorescent fittings with NiCad batteries which had poor energy efficiency and were expensive to maintain and test. With the goal of achieving a low cost of ownership and full site testing compliance, the Novatel Sydney Central Chief Engineer, Yi Ding, was looking for a solution.
In August 2019, Clevertronics were invited to the AccorHotels NSW/ACT Engineering Managers meeting to present on all things emergency lighting, including latest innovations, technology and meeting statutory compliance requirements. It was during this presentation Yi Ding was introduced to the Clevertronics XT HIVE monitored system; and the solution to his site challenges became apparent.
Challenges
When asked about the challenges currently facing them with manually testing the emergency lighting in the building Yi Ding said; “Testing now is difficult and expensive, we have to test out of hours so the contractor needs to come in at 4:30 in the morning and switch the lights off (not all circuits have test switches due to the age of the building) we also have to pay extra staff to be here at that time”. In addition, the existing baseline data that our compliance testing contractor has relating to circuit and switchboard details is incomplete and inadequate.”
Coupled with this was the high failure rates of the existing fittings resulting in unacceptable ongoing maintenance cost.
Solution
A Clevertronics XT HIVE Monitored System – One single HIVE controller and base fittings were installed as part of an incremental upgrade of the site emergency & exit lighting.
When asked why upgrading to XT Hive was the best option financially – Yi Ding commented: “We had a limited budget so we couldn’t do the whole building in one installation. With HIVE though we can begin with the infrastructure and a limited amount of fittings and then incrementally upgrade the building as fittings fail. This was an essential feature and XT Hive is the best value in achieving a bulletproof, low cost of ownership, monitored system.”
When asked why he agreed with Yi Ding’s recommendation of the Clevertronics XT HIVE solution, the installing contractor – Trent Cumines from Disc Electrical, a leading Sydney based electrical contracting business with extensive experience in hotels and commercial markets upgrading emergency and exit lighting said: “There are some challenges with the wiring onsite. We have worked with other RF and powerline monitored systems before, but due to the wiring/infrastructure on site, none of these were suitable. I did look at some other RF systems on the market, however they were more expensive from an installation standpoint and due to the building layout were not suitable to get effective communication to all areas.” “XT HIVE with its meshing was the only reliable solution”
Also from a support perspective, he wanted to use a brand that he could be confident had a proven reputation to support the system whole of life. XT HIVE backed by Clevertronics Advantage Lifetime Support (ALS) was the clear choice.
“We have worked with all manner of systems in the past, however the XT HIVE technology is backed by the best after sales support in the market which means we can execute the project with absolute certainty that our client will get the best outcome.
We have 100 fittings installed onsite which, with its meshing commissioned in less time than it took to get a coffee, we can now perform emergency exit light testing and certification safely without affecting the day to day running of the hotel, before expanding the network to the remainder of the building.”
The server and controller have been located in the engineering office at the base of the building, there are several exit and emergency fittings nearby to establish the mesh network to the rest of the building.
Daniel Garden the assistant chief engineer on the site goes on to say, ”The BMS and the XT HIVE server are on a separate dedicated network allowing remote access” this will enable the Clevertronics ALS team to assist in supporting the site remotely as the staged upgrade continues towards a fully monitored building.
Results
In March 2020 the initial installation of the first stage of the upgrade including 100 fittings, controller and server, was completed, on time and to budget with no disruption to hotel activities with the commissioning of the system concluded in a matter of minutes. The remaining older NiCad fittings will be replaced incrementally as they fail or as part of the planned site upgrade works. Due to each XT HIVE controller being able to manage 1000 fittings, no additional backbone hardware is required on site. The Clevertronics Advantage ALS program will now begin on this site, offering ongoing support for the life of the system.